Rancho San Diego Sewer Pump Station Rehabilitation

Rancho San Diego Sewer Pump Station pumps and pipes

Projects Rancho San Diego Sewer Pump Station Rehabilitation Rancho San Diego Sewer Pump Station Rehabilitation County of San Diego Rancho San Diego $4,439,596.91 2018 Description The Rancho San Diego Pump Station is located just off of a rural street owned and maintained by the County of San Diego. This station is a strategic element for […]

Black Mountain Ranch Unit 14 Improvements

Black Mountain Ranch - Unit 14 Improvements - storm drain work in progress

Projects Black Mountain Ranch Unit 14 Improvements Black Mountain Ranch Unit 14 Improvements Black Mountain Ranch LLC San Diego, 2 Miles East of Rancho Santa Fe $8,912,042 2018 Description Located among rolling hills just east of Rancho Santa Fe, this project included nearly 300 residences. TC Construction was contracted by Black Mountain Ranch LLC., to […]

Woodside Avenue Flood Control

Woodside Avenue Flood Control project puring concrete

Projects Woodside Flood Control Woodside Ave Flood Control Improvements County of San Diego Lakeside, CA $17,160,000 2017 Description Woodside Ave project consisted of constructing a large box culvert to eliminate historical flooding of the Riverview area in Lakeside, CA. The Riverview area includes light commercial, offices, apartments, and a school zone. The box culvert was […]

Sycamore Ranch

Sycamore Ranch grading work near bridge

Projects Sycamore Ranch Sycamore Ranch William Lyons Homes Fallbrook, CA $3,050,000 2017 Description The County of San Diego required several road improvements before a new housing development could be deemed complete. Two dead end roads had to be improved and connected over an existing river channel. The project involved the following improvements: Clearing and grubbing […]

Sorrento Mesa Recycled Water Pipeline

MACC Task Order No 15 Sorrento Mesa Recycled Water Pipeline trench work

Projects Sorrento Mesa Recycled Water Pipeline MACC Task Order No 15 Sorrento Mesa Recycled Water Pipeline City of San Diego Sorrento Mesa $2,245,419.00 2017 Description This project was awarded under the City of San Diego’s MACC (Multiple Award Construction Contract) program. TC Construction was selected from a pre-qualified group of five short-listed contractors to design […]

Harmony Grove Village Storm Drain

Harmony Grove Village drainage box culverts being placed

Projects Harmony Grove Village Storm Drain Ph 1 Harmony Grove Village Storm Drain Ph 1 CalAtlantic Group Harmony Grove Road, Escondido $10,826,832 2017 Description Harmony Grove Village is a 740 home development on a 460 acre site in rural Escondido, CA. Approximately 45,000 linear feet of 6 to 96 inch storm drain pipe and 540 […]

Sewer & Water Group 957

Sewer & Water Group 957 workers setting pipe in place

Projects Sewer & Water Group 957 Sewer & Water Group 957 City of San Diego Downtown San Diego $3,546,491 2016 Description This was a Design-Bid-Build project for the City of San Diego. The work consisted of: Removal and replacement of  8,200 feet of 8 to 20 inch water mains Fire hydrants and services, water services, […]

Genesee Avenue 18 Inch Sewer

Genesee Avenue 18" Sewer - train passes underneath work on bridge

Projects Genesee Avenue 18 Inch Sewer Genesee Avenue 18″ Sewer Garden Communities City of San Diego $3,710,396.35 2016 Description TC Construction was contracted to install over 4,500 linear feet of new 18 inch SDR 35 and 26 gravity sewer main for the new Costa Verde Center in University Town Center. The project was very complex […]

Poway Pump Station Secondary Power Source

Poway Pump Station Site Improvements view of pump

Projects Poway Pump Station Secondary Power Source Poway Pump Station Secondary Power Source Ramona Valley Water District Poway, CA $789,300 2015 Description Upgrades to the Poway Pump Station were necessary in order to reduce reliance on electricity, as was experienced during the 2007 wildfires. The project is located in a remote area of Poway at […]